Madison Library District
Trustee Board Meeting
Annual Budget Hearing
Minutes
Wednesday, 18 August 2010
The meeting was
called to order at 5:10pm by Blaine Robertson, chairman. Board members present
were Blaine Robertson, Gordon Timothy, Henry Benavidez, Jeniel Facer, Pam Beard, Judy Dewey, secretary, and Valerie
Vail, assistant director.
Remodel
Windows
in Old Library
The
first item of business was the condition of the window frames in the old
library. While replacing the glazing was in the contract, the frames were
expected to be reused; however, upon further investigation it was discovered
some of them were beyond use and the others were not in good condition after
thirty years. Judy showed the board two samples. One matched the frames in the
new addition (6” x 2”) and the other was smaller (4” x 2”). The existing frames
are 5 1/2” by 2”. Any savings incurred by using the smaller frame would be
eaten up in labor costs to clean the bricks of excess sealant and other stains,
so the board decided to go with the 6x2 frames. The 6x2 frame material would
take longer to arrive, but the subcontractor had already ordered it for the
clerestory windows. It was decided to use that material for the lower windows
and wait to use the additional material in the clerestory windows. The
contractor with make the clerestory openings as weather-tight as possible in
the meantime.
Jeniel
made the motion to use the 6x2 framing, Henry seconded the motion, and all but
one board member voted to approve. Gordon was the dissenting board member. Judy
was authorized to approve the change order request, assuming the final figure
corresponded with those presented to the board.
Furniture
- Inside Out
When
the bid for the furniture was prepared by CRSA, they did not indicate to the
bidders that the library project was in two parts; therefore, almost all the
furniture was delivered and had to be put in storage. The vendor, Inside Out,
needs to be paid because they have paid their vendors. All the furniture has
been delivered. That meant for the community room and the remodel is in storage
and the library now has the keys to the units. Judy will look at the furniture
to make certain it is indeed there (although determining if every piece is
there is not possible at this time). The board decided to go ahead and pay
Inside Out the balance of the purchase price since the company has threatened
to take it back and return it to their vendors. The library would then be out
approximately $30,000 in deposit. Judy said the extra money they will charge
for returning to Rexburg to install the rest of the furniture should be charged
to CRSA since they prepared the bid incorrectly.
Schedule
for Completion
The
building project is now scheduled for completion the first week in October.
Considering it was supposed to be completed by now, we are about six weeks
behind schedule.
Current
Issues: CRSA
CRSA
has accepted responsibility for $12,322 of the $82,150 of omissions and errors
so far in the construction project. Some monies have already been credited to
the library. CRSA is owed $11,115.49 which is 7% of the total upgrades and
unforeseen conditions so far. They will write us a check for the difference.
Pam
made the motion to accept the credit and cash payment that acknowledges CRSA’s
errors and their responsibility for those errors. Henry seconded the motion.
All voted in favor.
During
the meeting earlier in the afternoon with Wally and Kevin, they walked through
the old library. Wally observed several issues and made some changes on the
spot which should save the library money and solve some problems the contractor
has faced. Blaine asked that Wally make two more site visits before we are
through with the project as part of the settlement.
Addition
Forsgren
Associates Invoices
Judy
has been in communication with Forsgren Associates regarding their invoices
which total more than the agreed amount of $16,000. Forsgren has written a
letter outlining the issues. Some re-testing charges will be sent to the
contractor for payment; some charges (e.g., for floor flatness) are in addition
to the contract; some costs they will absorb as a donation to the library.
However, the figures in the letter had discrepancies and at the time of the
board meeting, a revised letter had not been received. Therefore, no decision
by the board was possible.
Current
Issues
Forbo
Flooring
The
welded seams in the Forbo linoleum flooring attract dirt and become unsightly.
The janitors have not been able to clean them to the library’s satisfaction.
This problem is being addressed by the architects and the custodians. It
appears the proper cleaner has not been used, but that cleaner has now been
procured. Judy will continue to monitor this situation.
Front
Entry Doors
Despite
multiple adjustments by the door subcontractor, the non-ADA front doors do not
close properly. Judy is of the opinion the hardware needs to be changed to a
type that does not allow the doors to remain open, and it appears the
weather-stripping is also interfering with the outside door not closing properly,
thus negating the weather-stripping function. This issue will continue to be
pursued with the contractor.
Floor
Problem in Childrens Programming Room
When
the floor was poured for the Childrens Programming Room (CPR), it should have
been poured so the east edge rested on the foundation of the adjoining
structure. Such was not done. The architects observed the same problem when the
foyer was poured but did not observe it at the entrance to the CPR. At this
point, nothing can be done to change it. It appears the floor slab has settled
because there is a ragged line where it meets the foundation and it shows
through the linoleum.
A
suggested solution is to replace the light colored linoleum with a dark
charcoal linoleum, through which the discrepancy in floor surfaces won’t show
as much, around three sides of the room so it looks like perhaps it was planned
that way.
The
problem at this point is we don’t know whether the slab will continue to move.
The contractor’s supervisor suggested “repairing” a patch next to the door,
which would involve taking up the old flooring, re-doing the floor prep, and
putting down another piece of the light gray linoleum. This will allow us to
observe whether the slab is still moving. Showcase Interiors agreed this is a
good experiment and their installer will do this in the next couple of weeks.
It may be that we need to wait a year to see what happens before we do the
“fix” with the darker linoleum.
Executive
Session
Pam
made the motion, pursuant to Idaho Code §67-2345(b), to adjourn into executive
session. Roll call vote was as follows: Jeniel, yes; Pam, yes; Blaine, yes;
Gordon, yes; Henry, yes. The meeting was then adjourned to discuss personnel
matters.
Budget
Hearing
Judy
had prepared a preliminary budget spreadsheet, listing incomes and expenses for
the current fiscal year, projecting income and expense for the balance of this
fiscal year, and proposing a budget for the 2010-2011 fiscal year.
Of
concern were salaries, maintenance, and utilities, the latter two being
somewhat unknowns because we have not physically occupied and operated in the
new library as a whole. Bids for custodial services will be requested; Judy is
working on the bid documents. Maintenance costs for the coming year were based
somewhat on current costs, multiplied by the expanded square footage. Utility
costs (gas, electricity, water, and telephone services) were estimated and then
more allowance made.
As
always, salaries are of concern. By state standards, our staff is paid less
than their counterparts in other parts of the state. At the same time, income
for our library is below state averages for libraries our size. This is due in
part to the agricultural land in the district on which lower property taxes are
paid. Additionally, there are substantial Bureau of Land Management and LDS
church holdings on which no property taxes are paid. Last year about 59% of the
total budget was spent on salaries. The proposed budget for this year showed
60% of the total being spent on salaries. The library is essentially a service
organization; service organizations spend a disproportionate amount on
salaries. Judy presented four scenarios for salaries: one based on a set dollar
amount per month and the other three based on percentage increases (1%, 2%, and
3%). Ultimately the board decided on the set dollar amount increase.
After
much discussion and analysis, it appearing that the budget as prepared would
suffice, Gordon made the motion to accept the budget, Jeniel seconded the
motion, and all voted in favor. As usual, no member of the public attended the
meeting so there were no public comments.
Approval
of Bills
The
checks having been signed and reviewed by the board members, Gordon made the
motion to approve the bills, Pam seconded the motion, and all voted in favor.
Personnel
Policy: Powers and Duties of the Board of Trustees
Because
so much time is being spent at board meetings on the building project, it was
decided to table this discussion until the building is completed and issues
relating thereto have been resolved.
Janitorial
Contract Bid
As
mentioned above, Judy is working on this bid and will advertise for it as soon
as the documents are ready.
Gordon
moved to adjourn the meeting at 7:38pm. The meeting was adjourned.
________________________________ ______________________________
Blaine Robertson, Chairman Judith M. Dewey,
Secretary